Your Aircraft
King Air 350
Soft goods refresh — seats, sidewalls, new wool carpet
FAA
Every material certified
In-house
Six craft stations
25+ yrs
Average artisan experience
Tyler, TX
One shop, start to finish
Project Progress
Overall completion
0%
Where your aircraft is
1
Design Approved
Feb 3
2
Strip-Out
Mar 20
3
Fabrication
In progress
4
Installation
Jul
5
Finishing
Aug
6
Certification & Delivery
Sep 18
On Dock
On the bench right now
Six stations, one shop
Upholstery
27 yrs / lead hands
In craft
Progress
78
Burnished cognac hide cut and stitched to pattern. 12 of 16 seat sets wrapped and inspected; quilted seat backs in progress.
Cabinetry & Veneer
31 yrs
In craft
Progress
54
Hand-matched walnut veneer laid across the credenza, side ledges and conference table. Satin topcoat scheduled next week.
Galley & Hardware
22 yrs
In craft
Progress
45
Stone-composite countertop templated. Satin-brass plating refinished for the galley and forward lav.
Plating & Trim
25 yrs
In craft
Progress
60
Seatbelt buckles and accent hardware stripped and refinished to a warm satin brass.
Avionics & Lighting
avionics bay
Staged
Progress
30
Cabin-management harness pulled and routed. LED valance fixtures on order, fit scheduled with installation.
Carpet & Flooring
queued
Queued
Progress
8
Wool loop carpet woven and cut. Holding for FAA burn certification before it goes into the cabin.
Materials & certification
Every hide approved before it sees a frame
  • Garrett leather — Midnight Blue — Certified
  • Wool carpet — Slate — On order
Investment
The numbers, in the open
Contract base
$360,000
Approved change orders
+$0
Current total
$360,000
Upgrade to quilted seat backs
+$42,000
Approved
Additional cabin LED zones
+$31,500
Approved
Conference table veneer change
+$23,000
Approved
Crew-rest fabric revision
+$28,000
Pending
Progress gallery
Photos from the floor
Cabin dry-fit — forward club
Seats and divan in build
Veneer matching on the bench
Photos added per project
Recent activity
Latest from the shop

Jun 28 · Induction
King Air 350 on dock; incoming evaluation complete with no discrepancies.

Jun 26 · Removal
Seats and sidewalls removed and tagged; carpet removal underway.

Currently in progress
Interior removal underway
Seats and sidewalls have been removed and tagged, and carpet removal is in progress. Your material selections are confirmed and on hand, so fabrication begins as soon as teardown is complete.
June 28, 2026
On Dock
Jun 24, 2026
Estimated Completion
Jul 30, 2026
Status
On track, no delays
Your Project Team
Marcus Cole
Project Lead, 22 years with Avtec