Contract total $487,500. Deposits must be received before work begins or materials are ordered.




Jul 2, 2026 · Finishing phase begun — cabinetry and veneer reinstalled.
Jun 24, 2026 · Galley quartz countertops installed (Change Order 01).
Jun 12, 2026 · Change Order 01 approved — galley refinish.
Jun 5, 2026 · All cabin materials passed FAR 25.853 burn testing — certificate posted to Documents.
May 26, 2026 · Aircraft on dock; strip-out completed May 30.
May 22, 2026 · Material selections approved by client.
May 1, 2026 · Work-scope deposit received — on-dock window reserved.
Cabinetry and veneer reinstalled; seats in final stitching and QC. Galley quartz installed under Change Order 01. Detail work and final inspections underway.